Group News
Media Reports
Information
Column
Path: Home >> News>> Goup News
Group News
     

Shagang 2500m3 BF Lining Shotcrete Construction was Finished

Issues Time:2012-01-17

On December 25, 2011, Allied Rongda company took lining shotcrete construction on Shagang 2500m3 BF. This construction part was the upper of the furnace stack. It took 12 hours, using 136 tons of materials. At present the blast furnace has returned to production, in normal operation.